How to calculate project margin in an agency
A project priced at €15,000 may look profitable when the quote is signed. Extra rounds of feedback and an additional supplier charge can reduce the expected margin well before the final invoice. Recalculate the margin when the scope or delivery plan changes so you can act while there’s still time.
The project margin formula
- Project margin in euros = project revenue excluding VAT − direct project costs.
- Project margin as a percentage of revenue = project margin ÷ project revenue excluding VAT × 100.
Multiply team hours by the internal hourly cost and add purchases, subcontracting and other costs directly attributable to the project. Use the same costing method across projects. This calculation covers direct costs. If revenue is zero, the percentage is undefined.
A worked example for a fixed-price project
The signed quote is €15,000 excluding VAT. You budget 120 hours at €60, or €7,200 in internal costs, plus €2,800 in purchases. The expected margin is €5,000 (33.3%).
Partway through, you forecast 30 extra hours at the same hourly cost and €700 in additional purchases. Without an approved change order, revenue stays at €15,000. The forecast total cost rises to €12,500 and the expected margin falls to €2,500 (16.7%).
What to review each week
Start with the signed quote, including approved changes. Add costs incurred to date to the estimated cost of completing the work. Count each purchase once, including orders that suppliers have yet to invoice. Compare the forecast margin with the original estimate and check invoiced amounts separately. If the margin drops, identify the reason and decide whether to adjust the scope, reschedule work or propose a change order.
How Furious helps protect project margins
With Furious, you can track each project’s forecast margin from the quote stage and drill down line by line. As the project progresses, the forecast updates using logged hours, committed purchases and remaining work. Configurable workflows and alerts flag variances, and AI helps you understand what’s driving them. That gives you time to adjust the schedule, purchases or scope while you can still protect the margin.